Bit of an update for progress works at RF Miles – oval reconstruction:
🐯Turf sand delivered for final levels
🐯Sub surface drainage installation 50% complete
🐯Perimeter spoon drain complete
🐯Oval fence almost complete
🐯Retaining walls installed along Seaford Road.
🐯In addition to this the netball courts have been line marked, goal posts in and it looks great. You’ll see a warm up goal post in the cricket nets as well which the cricket club were kind enough to support the installation of.
🐯 Pathways to the netball courts have been set out fir a concrete pour.
@etpturfmelb are in charge of the ground construction and are doing a cracking job. Thanks for all efforts ETP.
Monday the men join the Rettes back at Belvedere reserve for our pre season campaign. Any supporters are welcome to come down and see all the players in action.
Thursday night our netball department begin their pre season 2021 campaign as well.
Anyone has enquires about training or the RF Miles redevelopment please feel free to DM the club.